Construction of Gulak Township Road
Total Budget
₦500,000,000
Project Description
Construction of Gulak Township Road
Project Timeline
Planning
Dec 28, 2025Tender
Construction of Gulak Township Road
Award
Awarded to Supplier
Jul 29, 2020Contract
Contract signed
Planning Details
Project planning and budget information
Budget Amount
₦500,000,000
Budget Source
-
Rationale
Tender Information
Procurement tender details and documents
Construction of Gulak Township Road
Value
₦0
Procurement Method
Open
Start Date
Jul 07, 2020
End Date
Jul 17, 2020
Tender ID
ocds-adamawa-2025-247-tender-068
Involved Parties
All parties involved in the project
No Parties Information
Parties details have not been added to this project
Awards
Project awards and contract assignments
Construction of Gulak Township Road
Award Value
₦1,684,153,381
Awarded To
Triacta Nig. Ltd
172
Contracts
Contract agreements and modifications
Construction of Gulak Township Road
Contract Value
₦1,684,153,381
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-247-contract-275
Period
0 days